Advanced Industries
Wazee Electric – Multi-Phased Buildout
A 56,000 square-foot buildout of a Motor and Gearbox Repair Factory Building for Wazee Electric Timken Motors & Crane. Construction included providing up to 24” thickened pad structures for new and relocated owner equipment. Drilled and poured more than 50 new caissons inside the existing factory building as foundational supports for up to a 30-ton crane system, make-up air unit, and required smoke vents. The biggest challenge on this project was a 15’-0” deep reservoir pit to house their new VPI tanks and not undermine the building’s structure. Close coordination with the owner, their vendors, and construction trades was key to the overall success of the project and providing Wazee Electric with a fully functional motor repair shop.